Repair Methods

pressed_pilings

Pressed Pilings

Above you will find an illustration showing the process of repairing concrete slab foundations using Pressed Pilings. The objective being to transfer the load of the structure from unstable soils to more stable clays generally found 8 to 12 feet below the surface. This weight transference is acheived via piers placed 5 to 8 feet center to center, depending upon story height and construction type.

Advantages

Quick Installation

Typically this method of foundation repair can be performed in 1 to 3 days

Relatively Inexpensive

When compared with other methods of foundation repair

Durability

Outlasts Other Methods

Works for Almost Any Situation

Will repair most foundation problems

Do you need foundation repair or any other services we offer?

Construction Methodology

    1. INSTALLATION:
      1. Site Preparation:
        1. Client is informed of crew’s presence
        2. Pier locations are marked
        3. Plants, concrete, and other obstacles removed. (Only plants that need be are removed and placed in nursery buckets. Owners are encouraged to water them daily while out of the ground and after they are planted.)
      2. Excavation – Pier Construction:
        1. +/- 24″L X 24″W X 36″ deep hole is hand dug to expose exterior grade beam
        2. 6″ X 12″ cylinder is pressed one at a time until desired depth
        3. An 8″ X 8″ X 16″ solid cast block is placed center for jacking
        4. Plywood covers are placed over pier holes and a thorough clean-up is performed
    2. LEVELING: The purpose of this phase is to raise the piered portion of the structure to as near its original position as possible. Remember, few homes are poured/built perfectly level. There are many factors used in determining when the structure has been raised to its maximum potential. The foreman will be happy to go over these factors with you at that time.
      1. Jacking:
        1. A 25 ton mechanical jack is placed on pier-head and structure is jacked as previously described
        2. Precast, tested concrete blocks are placed on either side of the jack and steel shims are wedged between top block and bottom of grade beam
        3. Holes are backfilled
        4. Concrete is patched where it was broken out
        5. On lifts of 6″ of more, a mud slurry is often pumped under the slab to fill voids created by lifting the structure
        6. Plants are replanted and a thorough clean-up is performed

Rite-Way Foundation Company encourages customer participation whenever possible. We think you will find our management, office staff, foremen, and crews polite and helpful in assisting you. If you have any questions, please contact us.